109th Avenue Project Update – November 16, 2025
West Side of Highway 169 (Jefferson Highway intersection): The contractor is completing the final elements of the roundabout project, including installation of permanent signage, lighting, and pavement markings. For safety, the roadway will remain closed until all work is finished. We anticipate reopening by Thursday, November 20. Thank you for your continued patience as we complete this improvement.
************************************************************** Project Webpage: 109th Avenue Reconstruction Project Road Closure & Detour Information: View the 109th Detour (PDF) Questions? Stay Informed: Subscribe for project updates online, select “2025 109th Ave Reconstruction Project”. Improvements to 109th Avenue are being done in partnership with the City of Brooklyn Park.
|