109th Ave Reconstruction Project

109th Avenue Project Update – October 14, 2025


East Side of Highway 169 Road Closure Notice: 

The 109th Avenue closures at Xylon Lane and Winnetka Avenue have been rescheduled. We apologize for the delay. Construction is ever-changing, and weather permitting, thank you for your understanding and patience as we work to improve our community's infrastructure. To complete the installation, programming, and startup of the new traffic signals at Xylon Lane and Winnetka Avenue, the contractor will need daily closures of 109th Avenue east of Hwy 169 from 9am to 2pm on:

  • Wednesday, Oct. 15
  • Thursday, Oct. 16
  • Tuesday, Oct. 21

Please plan ahead and use an alternate route.

Road Closure & Detour Information:
View the 109th Detour (PDF)

West Side of Highway 169 (near the Jefferson Highway intersection): 

Concrete curb and gutter has been poured, and the contractor plans to start concrete paving for the roundabout later this week (weather permitting). 

**************************************************************

Project Webpage:
109th Avenue Reconstruction Project

Questions?

  • Email: ChamplinProjects2025@wsbeng.com
  • Call 763-270-3468 (monitored during business hours; responses within one business day)

Stay Informed:
Subscribe for project updates online, select “2025 109th Ave Reconstruction Project”.

Improvements to 109th Avenue are being done in partnership with the City of Brooklyn Park.

109th Ave Reconstruction Project
Share on Facebook
Share on Twitter
Share via Email

Copyright 2025 City of Champlin. All Rights Reserved.
11955 Champlin Drive Champlin, MN 55316

Powered by
CivicSend - A product of CivicPlus